Skip to content
NOWCAST 비바카지노 Viva News at Noon
Watch on Demand
코인카지노

I-MOVE Kentucky interstate project expected to be complete by fall 2024

I-MOVE Kentucky interstate project expected to be complete by fall 2024
AND WHEN IT COULD BE FINISHED. WHERE I맥스카지노M STANDING RIGHT NOW IS JUST A SMALL PIECE OF THIS BIG PROJECT. THIS WILL EVENTUALLY BE A BRIDGE, AND THE PROJECT MANAGER SAYS WHILE THEY EXPECTED THE CONSTRUCTION TO BE COMPLETE BY SUMMER 2024, THE NEW DATE WILL NOW BE THIS FALL. THERE맥스카지노S ABOUT 165,000 VEHICLES THAT THAT GO THROUGH THIS INTERCHANGE ON A DAILY BASIS. AND ALONG THIS ROUTE, FOR THE LAST FOUR YEARS, PEOPLE HAVE SEEN A PROJECT TO IMPROVE THE GENE SNYDER FREEWAY, I-71 AND I-64 IN THE MAKING. WE맥스카지노VE MADE A LOT OF PROGRESS. WE맥스카지노RE TRYING TO GET RID OF THE EXISTING RAMPS THE WAY THEY CURRENTLY SET, AND MAKE IT A MUCH BETTER FOR THE TRAVELING PUBLIC AS THEY DRIVE THROUGH THE PROJECT, MANAGER CHRIS SLOAN SAYS THE COMPLETION OF THIS PROJECT IS DELAYED UNTIL THE FALL BECAUSE THEY STARTED IN MARCH 2020. WITH THE PANDEMIC STALLING THEM FOR A WHILE. SINCE THEN, WE맥스카지노VE BEEN TRYING TO MAKE CONSTANT PROGRESS AND GET THIS PROJECT COMPLETED. IT맥스카지노S PAID FOR BY STATE AND FEDERAL HIGHWAY FUNDS. WITH THE ORIGINAL BUDGET STILL BEING INTACT. BUT EVEN WITH THE DELAYS, THE BUDGET SET, WE맥스카지노RE ON BUDGET, HE SAYS. MANY CREWS WORK TEN HOUR DAYS, 5 TO 6 DAYS A WEEK TO MOVE THIS PROJECT ALONG. UP THERE AT 71, THEY맥스카지노RE CURRENTLY FINISHING UP GRADING OPERATIONS. UM, ALL THE BRIDGES ARE BUILT. THEY맥스카지노RE, UH. SO WE GOT GRADING AND PAVEMENT FOR THE MOST PART LEFT ON 71. WE맥스카지노RE WORKING TOWARD THE COMPLETION. UH, YOU KNOW, ONCE AGAIN, BEAR WITH US. YOU KNOW, CONSTRUCTION IS GOING ON. THERE맥스카지노S PEOPLE OUT HERE EVEN ON TODAY WHERE WE HAVE A RAINY DAY, WE STILL HAVE PEOPLE WORKING AND WE맥스카지노LL CONTINUE TO HAVE THAT FOR THE REST OF UNTIL THE JOB IS
코인카지노
I-MOVE Kentucky interstate project expected to be complete by fall 2024
A large-scale highway project in Jefferson and Oldham counties has been four years in the making.Project manager Chris Slone said while they expected the construction to be complete by summer 2024, the new date will now be this fall.맥스카지노There맥스카지노s about 65,000 vehicles that go through this interchange on a daily basis,맥스카지노 said Slone. Along the route, for the last four years, people have seen a project to improve the Gene Snyder Freeway, Interstate 71 and I-64 in the making. 맥스카지노We've made a lot of progress. We're trying to get rid of the existing ramps the way they currently sit and make it much better for the traveling public as they drive through,맥스카지노 said Slone. Slone said the project was delayed until the fall because they started in March 2020 with the pandemic stalling them for a while. 맥스카지노Since then, we've been trying to make constant progress and get this project completed,맥스카지노 said Slone. The $180 million project is paid for by state and federal highway funds with the budget still being intact. 맥스카지노Even with the delays, the budget is set, and we맥스카지노re on budget,맥스카지노 said Slone. He said many crews work 10-hour days, five to six days a week, to move the project along. 맥스카지노Up there at 71, they are currently finishing upgrading operations. All the bridges are built there. So we have grading and pavement mostly left on 71,맥스카지노 said Slone, 맥스카지노We맥스카지노re working toward the completion and, you know, once again, bear with us. You know, the construction is going on. There's people out here, even on today, where we have a rainy day. We still have people working, and we'll continue to have that for the rest of 맥스카지노 until the job is complete.맥스카지노 I-MOVE Kentucky is the largest, single construction project in Kentucky since the Ohio River Bridges project was completed in 2016.

A large-scale highway project in Jefferson and Oldham counties has been four years in the making.

Project manager Chris Slone said while they expected the construction to be complete by summer 2024, the new date will now be this fall.

코인카지노

맥스카지노There맥스카지노s about 65,000 vehicles that go through this interchange on a daily basis,맥스카지노 said Slone.

Along the route, for the last four years, people have seen a project to improve the Gene Snyder Freeway, Interstate 71 and I-64 in the making.

맥스카지노We've made a lot of progress. We're trying to get rid of the existing ramps the way they currently sit and make it much better for the traveling public as they drive through,맥스카지노 said Slone.

Slone said the project was delayed until the fall because they started in March 2020 with the pandemic stalling them for a while.

맥스카지노Since then, we've been trying to make constant progress and get this project completed,맥스카지노 said Slone.

The $180 million project is paid for by state and federal highway funds with the budget still being intact.

맥스카지노Even with the delays, the budget is set, and we맥스카지노re on budget,맥스카지노 said Slone.

He said many crews work 10-hour days, five to six days a week, to move the project along.

맥스카지노Up there at 71, they are currently finishing upgrading operations. All the bridges are built there. So we have grading and pavement mostly left on 71,맥스카지노 said Slone, 맥스카지노We맥스카지노re working toward the completion and, you know, once again, bear with us. You know, the construction is going on. There's people out here, even on today, where we have a rainy day. We still have people working, and we'll continue to have that for the rest of 맥스카지노 until the job is complete.맥스카지노

I-MOVE Kentucky is the largest, single construction project in Kentucky since the Ohio River Bridges project was completed in 2016.